(Quang Binh News) The B&T Wind farm project has disbursed more than 1,800 billion VND

  • 01/03/2021
  • Information from B&T Wind Power Joint Stock Company said that, implementing the project of B&T wind farm cluster, so far, the unit has disbursed an amount of more than 1,800 billion VND of the total investment capital to implement the project. more than 8,000 billion VND.

    The B&T Wind Farm Cluster Project is implemented on sandy coastal areas in the territory of Quang Ninh and Le Thuy districts, including the following projects: BT-1 wind farm with a capacity of 109.2 MW and Farm BT-2 wind power phase 1 has a capacity of 100.8 MW.


    A team of engineers and workers are constructing the foundation of a turbine.


    According to a leader representative of B&T Wind Power Joint Stock Company, the unit is currently focusing heavily on directing and implementing the construction of the main items of the BT-1 Wind Power Farm Project, the BT-1 Wind Farm Project BT-2 wind power phase 1 with more than 700 officials, engineers, experts and workers on site.

    By February 24, 2021, the unit has disbursed an amount of more than VND 1,800 billion for construction contracts.


    A turbine foundation has been completed with concreting completed.


    Specifically, currently, these two projects have built 100% of the internal traffic routes with a total length of 48km; completed 36/50 turbine foundation and finished concrete 16/50 turbine foundation; building 61/73 foundations for 220Kv power line pylons; installed 6/73 electric poles 220Kv line; 2 power stations have completed 80% of the construction volume.


    A dedicated crane system is being installed to serve the installation of the turbine body.


    Regarding the BT-2 Wind Farm Project Phase 2 (the BT-2 Wind Farm Project Phase 2 has a capacity of 42 MW), B&T Wind Power Joint Stock Company 3 signed a memorandum of understanding for the first cooperation. with the Provincial People's Committee; approved by the Party Committee of the Provincial People's Committee and approved by the Standing Committee of the Provincial Party Committee; opinions of 19/20 relevant ministries. Currently, the company has completed the topographic survey and is conducting geological surveys, demining and completing other consulting contracts.

    According to Bui Thanh  (source of QBDT Newspaper)