(Investment News) AMI AC Renewables plans to invest 6 billion USD in wind power project in Quang Binh
This is information shared by Mr. Nguyen Nam Thang at the Quang Binh Provincial Investment Promotion Conference this morning (March 25) in Ho Chi Minh City.
As a foreign-invested enterprise established in 2017 on the basis of cooperation between AMI Renewables (Vietnam) and AC Energy (Philippines), AMI AC Renewables Company, the investor of a public B&T wind farm cluster capacity of 252 MW.
This is the first wind farm cluster in Quang Binh province and one of the largest onshore wind power projects in Vietnam that has been put into operation up to now.
In June 2018, the Quang Binh Provincial Investment Promotion Delegation led by Mr. Hoang Dang Quang, former Secretary of the Provincial Party Committee and currently Deputy Head of the Central Organizing Committee, took the initiative to go to Manila (Philippines). promote investment and invite Ayala Group to study and invest in wind power projects in Quang Binh.
Ayala Group, with nearly 200 years of establishment and development - is the oldest corporation and one of the largest multi-industry corporations in the Philippines, with total assets by the end of 2020 is 27 billion USD.
AC Energy is a subsidiary of Ayala Corporation and one of the fastest growing energy companies in the Philippines and in the region.
AC Energy aims to develop renewable energy above 5,000 MW by 2025.
A cluster of 252MW B&T wind farms of AMI AC Renewables in Quang Binh. (Source: Thai Hung).
At the meeting, the Chairman of Ayala Group was very impressed and highly appreciated that the top leaders of Quang Binh province took the initiative to go to the Philippines to promote investment invitations and showed a strong commitment in always accompanying the investors. invest when implementing legal procedures, compensation for site clearance and quickly solve all problems arising during project implementation.
On August 27, 2018, at the 2nd Quang Binh Provincial Investment Promotion Conference, under the witness of the Prime Minister, Quang Binh province awarded a Memorandum of Understanding on investment cooperation to AC Energy.
Accordingly, AC Energy through a joint venture in Vietnam, AMI AC Renewables Joint Stock Company, to invest and develop the B&T wind farm project with a capacity of 252 MW in Quang Binh with a total investment of about 380 million USD. .
After nearly 2 years of researching, surveying, assessing economic and technical, and carrying out legal procedures in accordance with the provisions of Vietnamese law, on June 25, 2020, the Prime Minister officially approved the supplement B&T wind farm cluster with a capacity of 252 MW in the revised Power Plan VII.
Less than two months after being approved for addition to the revised Power Plan VII, on August 18, 2020, the People's Committee of Quang Binh province granted an investment policy for the B&T wind farm cluster phase 1, with a capacity of 210 MW, including 50 turbines with a capacity of 4.2 MW each, supplied, installed and operated by contractor Vestas (Denmark) for 20 years.
More than 200 businesses attended the Quang Binh Provincial Investment Promotion Conference this morning. (Photo: Le Toan).
Total investment in phase 1 for this project is 6,845 billion VND. On September 20, 2020, the groundbreaking ceremony of the project took place on the occasion of the 17th Quang Binh Provincial Party Congress.
And by the end of December 2020, the entire site clearance work was completed in 8 communes of 2 districts of Quang Ninh and Le Thuy with a total area of land recovered for construction of nearly 80 hectares on a total planned area of nearly 3,000. ha, about 2 months earlier than planned.
"We did not need to wait for the completion of the phase 1 project, but confidently decided to submit to the People's Committee of Quang Binh province to continue investing in phase 2 with a capacity of 42 MW, a total investment of 1,268 billion VND", said Mr. Nguyen Nam Thang. recalled and said that this business has completed construction and installation, is legally and technically qualified to put the entire cluster of B&T wind farms in both phase 1 and phase 2 into commercial operation. from October 16, 2021.
Thus, the total time to complete the project of B&T wind farm with a capacity of 252 MW and disburse the entire 8,200 billion VND from the 2nd Investment Promotion Conference of Quang Binh province to completion and Commercial power generation is about 3 years 2 months.
For wind power investment, this progress result, according to General Director of AMI AC Renewables, is a rare feat in the world.
Mr. Nguyen Nam Thang, General Director of AMI AC Renewables company. (Photo: Le Toan)
General Director of AMI AC Renewables also said that the project of AMI AC Renewables was implemented during an extremely difficult and stressful period.
Specifically, they had to stop construction for nearly 45 days due to the impact of the historic flood in October 2020, the Covid-19 epidemic affecting transportation, disruption of the equipment supply chain and difficulties in construction. bringing foreign experts to Vietnam to install equipment and the preferential policy of FIT electricity purchase is only valid for 3 years (and expires on October 31, 2021).
In order to achieve the above-mentioned miracle results in a very difficult period, in addition to the high capacity and determination of the investor, AMI AC Renewables has expressed its respect and appreciation to all levels of government through various events. period of Quang Binh province.
Accordingly, the province has identified key projects, always accompanying businesses, working proactively, drastically, synchronously, quickly and in accordance with the law.
Not only that, the province is not rigid in completing the procedures for land use purpose conversion, compensation for site clearance quickly and without any complaints from the people and ensuring security and order. During the construction process in the two districts of Quang Ninh and Le Thuy, there was no need to stop construction any day during the outbreak of the Covid-19 epidemic.
Quang Binh Tax and Customs Department has guided wholeheartedly from the beginning to quickly clear the import clearance of equipment and refund 646.1 billion VAT in principle within 30 days after completing the inspection of tax refund documents. ,...
"With the success of this project and absolute belief in a better investment environment in Quang Binh, shareholders of AMI AC Renewables have completely trusted and decided to continue surveying and researching projects. We have proposed and are researching and developing the offshore wind power project AMI Quang Binh with a capacity of 2,400 MW and an estimated total investment of about 6 billion USD,” said Mr. Nguyen Nam Thang.
Related News
(KHANHHOA Online) AMI Khanh Hoa was selected to provide carbon credits for the 2024 Paris Olympics
Recently, the Paris 2024 Olympics announced the latest advancement in the games low carbon strategy. In addition to its ambition to reduce carbon emissions at the games, the organizing committee has developed a program to fund projects aimed at avoiding and capturing carbon emissions, with the aim of offsetting unavoidable emissions from this summer's sporting event.
See moreParis 2024 presents the latest advance in its low carbon strategy
Paris 2024 has set itself the goal of halving the carbon footprint of the Games compared with the average of London 2012 and Rio 2016. Less than a month before the Games begin, it is presenting the latest developments regarding its climate commitments in two key areas: reduction of Games-related emissions and support for carbon avoidance and capture projects.
See more(Department of Industry and Trade - Quang Binh) Inauguration of 252 MW B&T wind farm cluster in Quang Binh
On November 16, AMI AC Renewables Joint Stock Company (the parent company of B&T wind power joint stock company), officially held the inauguration ceremony of 252 MW B&T wind farm in Quang Ninh district and Le Thuy, Quang Binh province.
See more(Khanh Hoa News) AMI Khanh Hoa Energy Joint Stock Company is sponsored by the US Government to invest in a battery storage system (BESS) project.
The 3rd Vietnam-US Energy Security Dialogue was held from October 14 to 15, 2021 by Mr. Hoang Tien Dung, Director of the Department of Electricity and Renewable Energy, and Ms. Anna Shpitsberg, Deputy Assistant co-chaired by the Secretary of State of the United States. Dialogue consists of 4 sessions on the following topics: Energy Transformation; Developing the power grid and integrating Renewable Energy into the power system; Wind power development; and Investor selection for electricity and renewable energy projects. The Vietnam-US Energy Security Dialogue is a cooperation mechanism in the energy field between the Ministry of Industry and Trade of Vietnam and the US Department of State established and organized for the first time in March 2018.
See more(VoV.vn) Mobilizing a 100-ton crane to lift the derailed locomotive, opening the North-South railway line
VOV.VN - The North-South Railway was officially opened and operated again for more than 10 hours and was congested due to the derailment of cargo train SH4 at Sa Lung station, Vinh Long commune, Vinh Linh district, Quang Tri province.
See more(Quang Tri News) The North-South railway line opened after more than 10 hours of congestion
(QTO) - The North-South railway officially opened and operated again at 20:20 on the evening of July 17, after more than 10 hours of congestion due to the derailment of freight train SH4 at Sa Lung station (Vinh Vinh commune). Long, Vinh Linh district).
See more(Quang Binh News) The B&T Wind farm project has disbursed more than 1,800 billion VND
Information from B&T Wind Power Joint Stock Company said that, implementing the project of B&T wind farm cluster, so far, the unit has disbursed an amount of more than 1,800 billion VND of the total investment capital to implement the project. more than 8,000 billion VND.
See more(Vietnam Energy News) Signing credit contract to finance wind power project BT2
Vietcombank - Ky Dong branch and BT2 Wind Power Joint Stock Company have just held the signing ceremony of credit contract to finance BT2 wind power project, in Quang Binh province, with a capacity of 100.8 MW.
See more(CafeF VN) Big-scale investment projects in 2020
A series of large projects with an investment of trillions of dong are implemented and built in 2020 and are expected to contribute to the socio-economic development of localities.
See more(Investment News) Quang Binh: Commencement of the largest onshore wind farm cluster in Vietnam
B&T wind farm cluster has a total capital of nearly 9,000 billion VND, with a capacity of 210 MW, invested by AMI AC Renewables Company, and by experienced domestic and international contractors.
See more(Vecea.vn) Building a solar power plant – the story is now being told
VECEA: The race to build solar power plants shows that the soft mechanism of a private investor is always superior to an investor from the budget.
See more(CafeF VN) AMI and AC Energy put the BMT Dak Lak solar farm into the grid, starting commercial operation
BMT solar power project has an installed capacity of 30 Mwp, invested by a Joint Venture between AMI Joint Stock Company and AC Energy Group (Philippines). This is a typical renewable energy project of Dak Lak province.
See more